Project status

We’ve come so far!

Flamingo Kinderhospiz:

  • May 2022: Approval of the building rights agreement
  • October 2022: Planning application for the new building project
  • December 2022: Foundation of the Flamingo AG children’s hospice
  • April 2023: Receipt of the legally binding building permit
  • September 2023: Receipt of the building permit
  • December 5th 2023: Ground-breaking ceremony
  • Am 18. Dezember 2023 stimmt der Kantonsrat Zürich dem Beschluss des Regierungsrates zur Finanzierung von CHF 6 Mio. aus dem Gemeinnützigen Fonds zu.
  • Q1/2024: Excavation work, securing the excavation pit
  • Q2/2024: Shell construction basement
  • June 27, 2024: Laying of the foundation stone
  • Q3/Q4 2024: Shell construction lower floor, upper floors
  • 18. December 2024: shell construction ceremony
  • Q1/2025: Insulation of the façade
  • Q1/Q2 2025: Installation of the photovoltaic system
  • Q2/2025: Nasszellen/ Plattenarbeiten/ Akustikdecken/ Treppengeländer
  • Q3/2025: Floor coverings/ doors/ fixtures/ painting/ lighting
  • October 28, 2025: Handover of the construction project

We are working on it!

  • Building cleaning
  • Various guided tours of the new building
  • Technical inspections/acceptances
  • Fundraising and financing for operations
  • Establishing further collaborations and extensive networking
  • Q4/2025: Planned start of operations
  • January 06, 2026: First families come to the Flamingo
  • Preparations for the opening ceremony on May 30, 2026