Project status
FK_Haus_rund5
previous arrow
next arrow

We’ve come so far!

Flamingo Kinderhospiz:

  • May 2022: Approval of the building rights agreement
  • October 2022: Planning application for the new building project
  • December 2022: Foundation of the Flamingo AG children’s hospice
  • April 2023: Receipt of the legally binding building permit
  • September 2023: Receipt of the building permit
  • December 5th 2023: Ground-breaking ceremony
  • December 18, 2023: Zurich Cantonal Council approves the financing of CHF 6 million from the Public Benefit Fund.
  • Q1/2024: Excavation work, securing the excavation pit
  • Q2/2024: Shell construction basement
  • June 27, 2024: Laying of the foundation stone
  • Q3/Q4 2024: Shell construction lower floor, upper floors
  • 18. December 2024: shell construction ceremony
  • Q1/2025: Insulation of the façade
  • Q1/Q2 2025: Installation of the photovoltaic system
  • Q2/2025: Nasszellen/ Plattenarbeiten/ Akustikdecken/ Treppengeländer
  • Q3/2025: Floor coverings/ doors/ fixtures/ painting/ lighting
  • October 28, 2025: Handover of the construction project
  • Q4/2025: Start of operations
  • December 15, 2025: Start of personnel onboarding week

We are working on it!

  • Various guided tours of the new building
  • Fundraising and financing for operations
  • Establishing further collaborations and extensive networking
  • January 06, 2026: First families come to the Flamingo
  • Preparations for the opening ceremony on May 30, 2026

Image material

Photos of the new building

Photos of the groundbreaking ceremony

Photos of the laying of the foundation stone

Photos of the erection

Photos of the building handover/ handing over the keys